GE PT878GC Instrukcja Użytkownika Strona 44

  • Pobierz
  • Dodaj do moich podręczników
  • Drukuj
  • Strona
    / 308
  • Spis treści
  • BOOKMARKI
  • Oceniono. / 5. Na podstawie oceny klientów
Przeglądanie stron 43
April 2004
3-12
Installing the Transducers (cont.)
3. Slide the second mounting block to the calculated spacing
plus the initial scale number selected for the first mounting
block. For example:
a. Initial convenient number for the first mounting block =
1 cm or 1 in.
b. Spacing as calculated by the PT878GC = 0.5 in. or 12.5
mm
c. Second mounting block final location = 1 + 0.5 in. = 1.5 in.
or 1 cm + 1.25 cm = 2.25 cm
The overall spacing between yokes should be left edge to left
edge, or right edge to right edge. Figure 3-12 below shows typical
positioning.
Figure 3-12: Top View of V4 Fixture
with Both Transducers
4. In a similar manner, install the second transducer as shown in
Figure 3-12 above.
S
S
Przeglądanie stron 43
1 2 ... 39 40 41 42 43 44 45 46 47 48 49 ... 307 308

Komentarze do niniejszej Instrukcji

Brak uwag